Our team installed two shot blasting chambers at the manufacturing facility of automotive components in the Kostanay region of the Republic of Kazakhstan. The work was carried out under the supervision of chief engineers.

For the installation, we used:
- Truck crane with lifting capacity of 16 tonnes
- Truck crane with lifting capacity of 50 tonnes
- Aerial elevator
- Forklift – 2 units
- Scissor elevator – 2 units
- Power tool
Assembly and installation of blasting equipment
Installation of a shot blasting system in Kazakhstan
Key project tasks
- Development of the Work Execution Plan (WEP)
- Assembly and installation of two shot blasting machines
- Exhaust stack installation