Our team installed two abrasive blasting units at a machinery manufacturing enterprise in the Republic of Kazakhstan. We also installed a stack and a carbon dioxide storage tank. The scope of work included pipeline welding and NDT inspection of the welded joints.
Project Features
The work schedule was adjusted during the project, but we successfully adapted to the client’s needs. We quickly mobilized personnel and equipment to the site and completed the bulk of the work on time.
The equipment was installed under the supervision of chief engineers. The “100 TONN.KZ” site management established effective communication with the manufacturer’s representatives. Our proposals for optimizing the technology were accepted.
The following equipment was used on site:
- Truck crane with a lifting capacity of 25 tonnes
- Truck crane with lifting capacity of 50 tonnes
- Boom lift
- Forklift
- Scissor lift
Key project tasks
- Development of the Work Execution Plan
- Assembly and installation of two abrasive blasting units
- Chimney installation
- Installation of a liquid carbon dioxide tank
- Pipeline welding
- Radiographic inspection of welds