Our team installed two abrasive blasting units at a machinery manufacturing enterprise in the Republic of Kazakhstan. We also installed a chimney stack and a carbon dioxide tank. Pipeline welding was carried out, along with non-destructive testing of welded joints.
Project Features
The work schedule was adjusted during the project, but we successfully adapted to the client’s needs. We quickly mobilized personnel and equipment to the site and completed the bulk of the work on time.
The equipment was installed under the supervision of chief engineers. The “100 TONN MONTAGE” site management established effective communication with the manufacturer’s representatives. Our proposals for optimizing the technology were accepted.
The following equipment was used on site:
- Truck crane with a lifting capacity of 25 tons
- Truck crane with lifting capacity of 50 tons
- Aerial elevator
- Forklift
- Scissor lift
Key project tasks
- Development of the Work Execution Plan (WEP / PPR)
- Assembly and installation of two abrasive blasting units
- Chimney installation
- Installation of a liquid carbon dioxide tank
- Pipeline welding
- Radiographic inspection of welds