100 TONN.KZ specialists moved and installed six RQQ machines at a railway wheel manufacturing plant in Ekibastuz. The weight of each unit was 39 tons. A 200 t gantry system was used for the project.
The main challenge lay in the numerous pits located across the floor. To eliminate risks, our specialists designed reinforcements for the pits and accurately positioned the gantry system’s rail guides.
Thanks to the experience of the 100 TONN team, the project was completed ahead of schedule, with high quality and without errors. This provided the client with additional time for the plant’s launch.
List of key operations:
- Development of the Work Execution Plan (WEP) in accordance with the requirements of the Republic of Kazakhstan.
- Lifting and moving RQQ machines
- Installation of the equipment on the foundation