In June 2016, the company “100 TONN MONTAGE” carried out unloading, de-preservation, large-scale assembly, and installation on vibration supports of four Wartsila gas generator units in the Republic of Kazakhstan.

By utilizing the GP500 gantry system, the general contractor was able to begin equipment installation after the building’s load-bearing steel structures were in place, while simultaneously starting the installation of sandwich panels. This technology significantly reduced the overall project timeline.
The engineers at “100 TONN” implemented an effective technical solution that further accelerated the work. Before the low-bed trailer moved into position for unloading, a section of the gantry track guide (rails) was dismantled. After the load was lifted and the trailer exited, the removed track section was reinstalled, allowing the gantry to travel over it while carrying the load. The complexity of the project had lain in the simultaneous execution of construction and installation works on site, as well as in the precise positioning of the gas generator units on vibration supports with a tolerance of 1 mm.
Thanks to careful project planning, experience with Wartsila equipment and teamwork, 100 TONN MONTAGE perfectly managed to complete the work on schedule.