100 TONN.KZ transported a tobacco drum across the plant site, positioned the equipment in its design location, and secured it with nuts. The company’s team also dismantled the existing drum and moved it to the warehouse.

Project Features
Each drum weighed 17 t. For the rigging operation, the team used a GP60 gantry system, a set of machinery skates with a capacity of up to 80 t, low-profile jacks, and manual winches.

Key project tasks
- Unloading the container with the drum from the truck
- Transporting the container from the gate to the installation site in the workshop
- Opening the container and removing the drum from the frame
- Installing the drum
- Fabrication of a support cradle. Lowering and moving the used drum onto the cradle
- Transporting the dismantled drum out of the workshop